Question

1 Approved Answer

This is the information help me finish this 3,4,5 Background Information: A company produces an end item ' F, which is composed of three subassemblies:

This is the information image text in transcribed
help me finish this
image text in transcribed3,4,5
Background Information: A company produces an end item ' F, which is composed of three subassemblies: 2 units of A,1 unit of B, and 3 units of C.A is made of 3Ms and 2Ns; B is assembled using 1P and 2Qs; and C is made of 2Xs and 3Ys. Onhand inventories are 120As and 220Ns. Scheduled receipts are 120Ns at the start of week 2 . Lead times are one week for all subassemblies and two weeks for all components. Final assembly of F requires one week. 1. Fill in the following table to prepare a master production schedule (MPS) for end item ' F ' using the lot-for-lot rule. The beginning inventory for F is 112 units; the forecast and committed customer orders for end item F are provided in the table. [4 marks] 3. Use your master production schedule (MPS) in Table 1 to develop a material requirement plan (MRP) for the [4 marks] 4. Use your MRP schedule for the subassembly A to develop material requirements plan (MRP) for the component N using the lot-for-lot ordering policy. [4 marks] You are required to calculate the total inventory cost for the component N during the eight weeks. Note that, for each week, the inventory cost includes a fixed cost and a holding cost. We assume that the per order fixed cost is $100/ order, and the unit holding cost is $1 per item per week. The fixed cost is incurred each time when the firm places an order. More precisely, if the firm places an order at the beginning of a week, then the firm incurs the fixed cost for this week; otherwise, the fixed cost for the week is zero. The holding cost is calculated according to the number of remaining items at the end of each week. For example, if 10 units of the component N are remaining at the end of a week, then the holding cost for this week is 10x $1=$10. [4 marks]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Decision Support And Business Intelligence Systems

Authors: David King, Ting Peng Liang

9th Edition

013610729X, 9780136107293

More Books

Students also viewed these General Management questions