Question
1 Approved Answer
This is the sum of all the long tasks in a project. Because those tasks need to occur in order, this drives the shortest possible
This is the sum of all the long tasks in a project. Because those tasks need to occur in order, this drives the shortest possible project timeline. Critical route Milestones Critical path Least necess