this picture shows the EVM data of a project. The budget is $100,000 and the project duration is of 10 months. It started on 1
this picture shows the EVM data of a project. The budget is $100,000 and the project duration is of 10 months. It started on 1st Jan 2008. It is now 31st July and the table shown the actual cost (AC) and earned values (EV). Activity Incorporate feedback is 75% completed as today.
Activity | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct |
Plan project | 2,000 | 2,000 |
|
|
|
|
|
|
|
|
Analyze requirements |
| 4,000 | 6,000 |
|
|
|
|
|
|
|
Develop Data Model |
|
| 3,000 | 3,000 |
|
|
|
|
|
|
Design database |
|
|
| 6,000 | 6,000 |
|
|
|
|
|
Design forms &reports |
|
|
|
| 8,000 | 8,000 |
|
|
|
|
Construct prototype |
|
|
|
|
| 10,000 |
|
|
|
|
Test/evaluate prototype |
|
|
|
|
| 4,000 | 6,000 |
|
|
|
Incorporate feedback |
|
|
|
|
|
| 4,000 |
|
|
|
Test system |
|
|
|
|
|
|
| 10,000 | 9,000 | 9,000 |
Monthly AC | 2,000 | 6,000 | 8,000 | 9,000 | 13,000 | 21,000 | 10,000 |
|
|
|
Monthly EV | 2,000 | 6,000 | 9,000 | 9,000 | 14,000 | 22,000 |
|
|
|
|
- What is the Earned Value (EV) in July?
- What is the Cumulative Earned Value (EV) as of 31st July 2008
- What is the Cumulative Actual Cost (AC) as of 31st July 2008
- What is the Cumulative Planned Value (PV) as of 31st July 2008
- Calculate the Cost Variance (CV) as of 31st July 2008.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started