Question
1 Approved Answer
This table will cover information for Q1-Q3 year project A project B 0 -1000 -900 1 300 240 2 300 240 3 300 240 4
This table will cover information for Q1-Q3
year | project A | project B |
0 | -1000 | -900 |
1 | 300 | 240 |
2 | 300 | 240 |
3 | 300 | 240 |
4 | 300 | 240 |
5 | 300 | 240 |
For above project, interest rate is 10%
Q1 what is NPV of project A
2) q2 what is IRR of project b
3) NPV for A is higher than NPV for project B
True
False