Thomas Surfson, the manager of a Wilmington based surf boards manufacturing Company has developed monthly forecasts for a family of surf boards. Data for the

Thomas Surfson, the manager of a Wilmington based surf boards manufacturing Company has developed monthly forecasts for a family of surf boards. Data for the 6-month period January to June are presented in the following Tables. He needs to develop an aggregate production plan. (Questions 4,5,6,7)

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Production Days

20

20

20

20

20

20

Production per day

50

50

50

50

50

50

Cost and other Information

Inventory holding cost

Subcontracting cost

Average Pay rate

Overtime pay rate

Labor hours to produce one unit

Hiring cost

Layoff cost

$1/unit/month

$20 per unit

$10/hour

$17/hour

1.6 hours/ unit

$300/person

$600/person

One possible plan is to maintain a constant work force throughout the 6 month period, 10 employees. Each employee can produce 5 units in one day (8 hours).

Use the following Table as a reference to calculate the total cost for this plan (maintain a constant work force throughout the 6 month period). (Level Strategy)

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Produce

Beginning Inventory

Ending Inventory

Total Inventory Holding Cost is ___.

Group of answer choices

9,000

8,000

1,800

1,700

8,500

Flag question: Question 5

Question 510 pts

Thomas Surfson, the manager of a Wilmington based surf boards manufacturing Company has developed monthly forecasts for a family of surf boards. Data for the 6-month period January to June are presented in the following Tables. He needs to develop an aggregate production plan.

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Production Days

20

20

20

20

20

20

Production per day

50

50

50

50

50

50

Cost and other Information

Inventory holding cost

Subcontracting cost

Average Pay rate

Overtime pay rate

Labor hours to produce one unit

Hiring cost

Layoff cost

$1/unit/month

$20 per unit

$10/hour

$17/hour

1.6 hours/ unit

$300/person

$600/person

One possible plan is to maintain a constant work force throughout the 6 month period, 10 employees. Each employee can produce 5 units in one day (8 hours).

Use the following Table as a reference to calculate the total cost for this plan (maintain a constant work force throughout the 6 month period). (Level Strategy)

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Produce

Beginning Inventory

Ending Inventory

Total Regular time labor cost is ___.

Group of answer choices

94,000

96,000

17,000

18,000

85,000

Flag question: Question 6

Question 610 pts

Thomas Surfson, the manager of a Wilmington based surf boards manufacturing Company has developed monthly forecasts for a family of surf boards. Data for the 6-month period January to June are presented in the following Tables. He needs to develop an aggregate production plan.

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Production Days

20

20

20

20

20

20

Production per day

50

50

50

50

50

50

Cost and other Information

Inventory holding cost

Subcontracting cost

Average Pay rate

Overtime pay rate

Labor hours to produce one unit

Hiring cost

Layoff cost

$1/unit/month

$20 per unit

$10/hour

$17/hour

1.6 hours/ unit

$300/person

$600/person

Another possible plan is to produce exactly what the demand is (Chase Strategy) by hiring and layoffs as needed. Each employee can produce 5 units in one day (8 hours). They have 10 employees in the beginning of January.

Use the following Table as a reference to calculate the total cost for this plan.

Month

January

February

March

April

May

June

Expected Demand

900

700

800

1000

1500

1100

Produce

Production Days

20

20

20

20

20

20

Number of Employees Needed

Number of employees hired

Number of employees laid off

Total hiring cost is ___.

Group of answer choices

2,400

600

2,100

300

1,500

Total lay off cost is ___.

Group of answer choices

1,200

600

1,800

3,600

4,200

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Materiality In Financial Reporting An Integrative Perspective

Authors: Francesco Bellandi

1st Edition

178743737X, 9781787437371

More Books

Students also viewed these Accounting questions