Three different estimates were made for the duration of an activity. Those estimated duration values are given in the table below: Optimistic duration 7 (weeks)
Three different estimates were made for the duration of an activity. Those estimated duration values are given in the table below: Optimistic duration 7 (weeks) Pessimistic duration 17 (weeks) Most likely duration 9 (weeks) Required: Determine the expected duration (in weeks) of the activity under consideration