Through a well-run value management process good ideas and possible changes materialize. During which project phase would it be best to implement any change? Group
Through a well-run value management process good ideas and possible changes materialize. During which project phase would it be best to implement any change? Group of answer choices Design Bid and award Construction Closeout and turnover