Tigasin Builders Company began its construction activities in 2017. At the end of its first year's operation, the following projects (and other relevant information) are
Tigasin Builders Company began its construction activities in 2017. At the end of its first
year's operation, the following projects (and other relevant information) are still
uncompleted:
Project Contract
Price
Billings thru
12/31
Collections
thru 12/31
Actual costs
thru 12/31
Est cost to
Complete, 12/31
Angeles City 15,000,000 10,000,000 9,000,000 12,400,000 3,100,000
Palo City 17,500,000 5,500,000 5,250,000 3,390,000 13,560,000
Tigasin Builders will use the cost-to-cost percentage of completion in accounting for the
Angeles City project, while the cost recovery method will be used for the Palo City
project. 1. Compute the Construction Revenue to be recognized by Tigasin Builders for the
Angeles City project in 2017. 2. Determine how (1) the Angeles City Project and (2) the Palo City Project will be shown
on the year-end balance sheet.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started