Question

1 Approved Answer

Time (Days) 8) Activity Immediate Predecessor A 2 B C 5 1 B D E A, D F C 10 3 6 8 G

image text in transcribed

Time (Days) 8) Activity Immediate Predecessor A 2 B C 5 1 B D E A, D F C 10 3 6 8 G E, F What is the expected project completion time in days? List the slack times. 9) Activity A BC Immediate Predecessor Normal Time (Months) Crash Time (Months) Normal Cost Crash Cost 6 - 7 45 $2,000 $2,400 3,000 3,500 A 7 6 1,000 1,300 B 6 4 2,000 2,600 D 9 8 8,800 9,000 Based on the above, list the crash cost per month for the different activities. What is the least cost of reducing the project completion date by 3 months? D E

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Chuck Williams

4th Edition

978-0324316797, 0324316798

More Books

Students also viewed these General Management questions

Question

Who do you usually turn to for help when facing a problem?

Answered: 1 week ago

Question

How might social change occur?

Answered: 1 week ago

Question

How would you set up an experiment with a sample of 40 students?

Answered: 1 week ago