Time (Weeks) Normal Crash Normal Crash Immediate Time Time Cost Cost Crash Cost per Activity Predecessor (NT) (CT) (NC) (CC) NT-CT CC-NC WEEK A
Time (Weeks) Normal Crash Normal Crash Immediate Time Time Cost Cost Crash Cost per Activity Predecessor (NT) (CT) (NC) (CC) NT-CT CC-NC WEEK A 3 2 $300 $400 1 $100 $100 B - 10 9 $300 $700 1 $400 $400 C A 4 2 $500 $600 2 $100 $50 D B, C 5 3 $150 $225 1 $75 $75 E D 2 1 $450 $475 1 $25 $25 F B 6 2 $200 $800 4 $600 $150 A (3) C (4) D (5) E (2) B (10) F (6)