Question

1 Approved Answer

Timeline Project Stage Start Finish Duration 1. Internal Analysis January March 60 days 2. System Configuration April May 40 days 3. Data Preparation and Cleansing

  1. Timeline
Project Stage Start Finish Duration
1. Internal Analysis January March 60 days
2. System Configuration April May 40 days
3. Data Preparation and Cleansing June October 100 days
4. Development August September 30 days
5. Testing September October 30 days
6. Training and Support October November 20 days
7. Go Live Activities November December 20 days
8. Close Down and Review December January 20 days
  1. Task no.
  2. (WBS)
  1. Task Name
  1. Predecessor
  2. relationship
  1. Duration
  1. Resources required
  1. Days
  1. Human
  1. Material
  1. Equipment
1. Internal Analysis
1.1 User processes Project approval 15 Business analyst N/A Process writing software
1.2 Identify data requirements Develop an overview of user processes 15 Business analyst N/A Data collection tools
1.3 Analyse stakeholder needs Identify data requirements 15 Business analyst N/A Stakeholder analysis tools
1.4 Review current business processes Analyse stakeholder needs 15 Business analyst, Operations Manager N/A Process review tools
2 System Configuration
2.1 Software purchase Project approval 1 IT Manager N/A N/A
2.2 Determine hardware requirements Purchase Sage CRM 5 IT Manager N/A N/A
2.3 Obtain hardware and peripherals Determine hardware requirements 10 IT Manager Hardware N/A
2.4 Determine customisation requirements Obtain hardware and peripherals 10 IT Manager, Business Analyst N/A N/A
2.5 Approve and finalise customisation specifications Determine customisation requirements 14 IT Manager, Review team N/A N/A
3 Data preparation and cleansing
3.1 Review and clean data Approve and finalise customisation specifications 100 Data analysts N/A Data cleansing tools
4 Development
4.1 Determine security roles Review and clean data 5 Development team N/A N/A
4.2 Complete system configuration Determine security roles 5 Development team N/A Configuration tools
4.3 Finalise customisation code Complete system configuration 5 Development team N/A Development tools
4.4 Conduct acceptance testing Finalise customisation code 5 QA team Testing scripts Testing environment
4.5 Begin developing data migration scripts Conduct acceptance testing 5 Data Analyst, IT Developer Migration scripts Development tools
4.6 Configure system settings Begin developing data migration scripts 5 IT Developer N/A Configuration tools
5 Testing
5.1 Conduct infrastructure testing Configure system settings 6 Testing team N/A Testing environment
5.2 Conduct system testing Conduct infrastructure testing 6 Testing team N/A Testing environment
5.3 Conduct user acceptance testing (UAT) Conduct system testing 6 Testing team, Users N/A Testing environment
5.4 Conduct pilot group testing Conduct user acceptance testing (UAT) 6 Testing team, Pilot group N/A Testing environment
5.5 Finish customisation

Conduct pilot group testing

6 Development team Customisation specifications Development tools
6 Training and support
6.1 Administrator training Development 4 Training manager and consultants Training materials Sage CRM
6.2 Schedule and deliver user training Schedule and deliver administrator training 4 Training manager, Consultants Training materials Sage CRM
6.3 Develop process flows for CRM use Schedule and deliver user training 4 Business Analyst Process flow templates N/A
6.4 Develop specific user policies and procedures Develop process flows for CRM use 4 Policy Writer Policy templates N/A
6.5 Develop quick help guides Develop specific user policies and procedures 4 Documentation Specialist Guide templates N/A
7 Go Live
7.1 Migrate data Provide ongoing help desk support 10 Data Analyst, IT Developer Migration scripts Development tools
7.2 Release final deliverables Migrate data 10 Project Manager, IT Manager N/A Release tools
8 Close down and review
8.1 Conduct technical support handover Release final deliverables 4 IT Manager, Support Team Handover documentation N/A
8.2 Conduct post-implementation review Conduct technical support handover 4 Project Manager, Key Stakeholders Review templates N/A
8.3 Review final communication plan Conduct post-implementation review 3 Communication Manager Communication plan N/A
8.4 Produce end of project report Review final communication plan 3 Project Manager Report templates N/A
8.5 Perform change management review Produce end of project report 3 Change Manager Review templates N/A
8.6 Ensure all required documentation is distributed Perform change management review 3 Project Manager Documentation N/A

Develop the project schedule using appropriate software and techniques. It is recommended that you use a simple Gantt Chart

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cases In Communications Law

Authors: Michael T Simpson, John Zelezny

6th Edition

1111791910, 9781111791919

More Books

Students also viewed these General Management questions

Question

What is the factor form of f ( x ) = 8 x 3 + 2 0 x 2 - 2 x - 5

Answered: 1 week ago