TIMES (days) Activity Start Node Finish Node OPTIMISTIC t o MOST LIKELY t m PESSIMISTIC t p A 1 2 25 31 43 B 1
TIMES (days) |
| ||||
Activity | Start Node | Finish Node | OPTIMISTIC to | MOST LIKELY tm | PESSIMISTIC tp |
A | 1 | 2 | 25 | 31 | 43 |
B | 1 | 3 | 24 | 30 | 48 |
C | 2 | 5 | 18 | 30 | 42 |
D | 3 | 4 | 29 | 53 | 77 |
E | 4 | 5 | 13 | 25 | 61 |
Given the Activity on Arrow Diagram and the data found in the table above, calculate each of the following values: Activity A.........te= 32 Standard Deviation = 3 Activity B.........te=
Standard Deviation =
Activity C.........te=
Standard Deviation =
Activity D.........te=
Standard Deviation =
Activity E.........te=
Standard Deviation = 8 Path 1 - 2 - 5 Mean Time =
Standard Deviation =5 Path 1 - 3 - 4 - 5 Mean Time =
Standard Deviation =
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started