To make a MPS for the data given by (period, Forecast Demand) as: (1, 1600), (2, 1500), (3, 1300), (4, 1600), (5, 1500), (6, 1400),
To make a MPS for the data given by (period, Forecast Demand) as: (1, 1600), (2, 1500), (3, 1300), (4, 1600), (5, 1500), (6, 1400), if the maximum production is 2000 (if you decide to schedule a production in a period, the maximum quantity you can make is 2000 pieces), and if the lot size is 500, which MPS is not possible in week 2? The beginning Projected Available is 500