Today is February 1 and you have now entered into a Lease for the Boa Street property and need to kick - off your project.

Today is February 1 and you have now entered into a Lease for the Boa Street property and need to
kick-off your project.
You take this opportunity to consider what you are trying to accomplish with the fit-out and move into
the new building, as you know that Office 2050 is very important to Taste-e-Pill. You meet with Lucy and
she explains that the key to the project from a tactical point of view is to meet the schedule and budget
of course. But, she explains that key Stakeholders at The Taste-e-Pill tend to move slowly regardless of
the importance of a project and that your job is to find a way to get this done on time. The biggest
issue is that the Business Unit leaders want to have a say in the design of the space, in order to balance
quality and density issues for recruiting talent. In the past, such approvals take 30 days, and have
occurred at either SD or DD phases.
You know that the move-in date for all the new employees must be no later than the start of Q4.
You also review the Lease, and understand that the Landlord will be completing the construction for
Taste-e-Pill, using your architects design. All FF+E will be sourced by Taste-e-Pill, but also installed by
the Landlord.
You next meet with various internal groups at Taste-e-Pill, discuss with the Landlord and the architect,
and come away with the following information:
Landlord
o Construction will take 90 days after demolition and after CDs
o Demolition is 30 days, but can start after SDs are complete
o IT install is 21 days after the equipment arrives, and after Construction complete
o Other FF+E is 14 days from Construction complete
Architect
o SDs will take 21 days
o DDs will take 21 days
o CDs will take 21 days
IT
o Need to order long lead time equipment right away: and will take 4 months to arrive
o Long lead time items cannot be specified until SDs are complete
Facilities
o Move in will take 14 days from Landlord being 100% complete
Assignment:
Please create an MS Project schedule using the above information. Make sure to add in any decision
points that are needed at the Strategic level (success measures) from any key Stakeholders (and identify
same.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions