Tom is working on a project to develop and deliver inventory management software to Canadian Hardware Inc. The critical time is 80 days. Canadian Hardware
Tom is working on a project to develop and deliver inventory management software to Canadian Hardware Inc. The critical time is 80 days. Canadian Hardware Inc. has indicated that they must have the finished product in 100 days. The Project Float is
80 days
100 days
20 days
Zero project float