Question
Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to
Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory.
In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months:
Month1234Quality control measures:Number of defects19317113293Number of warranty claims54473835Number of customer complaints1101048766Material control measures:Purchase order lead time10 days9 days7 days5 daysScrap as a percent of total cost1%1%2%3%Machine performance measures:Machine downtime as a percentage of availability4%5%5%8%Use as a percentage of availability95%92%89%85%Setup time (hours)10121314Delivery performance measures:Throughput time????Manufacturing cycle efficiency (MCE)????Delivery cycle time????Percentage of on-time deliveries96%95%92%89%
The president has read in industry journals that throughput time, MCE, and delivery cycle time are important measures of performance, but no one is sure how they are computed. You have been asked to assist the company, and you have gathered the following data relating to these measures:
Average per Month
(in days)1234Wait time per order before start
of production8.010.711.013.0Inspection time per unit0.70.60.60.6Process time per unit2.82.62.41.1Queue time per unit4.14.46.38.4Move time per unit0.40.70.70.9
Required:
1-a. Compute the throughput time for each month.
1-b. Compute the manufacturing cycle efficiency (MCE) for each month.
1-c. Compute the delivery cycle time for each month.
3-a. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 5 the inspection time, process time, and so forth, are the same as for month 4, except that the company is able to completely eliminate the queue time during production using Lean Production. Compute the new throughput time and MCE.
3-b. Refer to the inspection time, process time, and so forth, given for month 4. Assume that in month 6 the inspection time, process time, and so forth, are the same as in month 4, except that the company is able to eliminate both the queue time during production and the inspection time using Lean Production. Compute the new throughput time and MCE
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started