Question
Tony Nunzio, a building contractor, builds parking garages. His company is capable of building multiple parking garages at once. Nunzio has budgeted for an expected
Tony Nunzio, a building contractor, builds parking garages.
His company is capable of building multiple parking garages at once. Nunzio has budgeted for an expected number of parking garages in 2015 as follows:
Direct Materials | $2,000,000 |
Direct Labor | 3,000,000 |
Job construction overhead - Variable Costs | 2,000,000 |
Job construction overhead - Fixed Costs | 1,000,000 |
Cost of jobs | $8,000,000 |
Selling and Administrative Costs - Variable | 2,500,000 |
Selling and Administrative Costs - Fixed | 1,500,000 |
Total Costs | $12,000,000 |
---|
Nunzio wants an operating income of $2,000,000 for 2015.
Required:
1. Compute the average target markup percentage for setting prices as a percentage of the following:
a) Direct Materials plus Direct Labor
b) The full "Cost of Jobs"
c) The Variable "Cost of Jobs"
d) The full "Cost of Jobs" plus Selling and Administrative Costs
2. Why are these calculations important?
Step by Step Solution
3.57 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
Answer Direct Materials 2000000 Direct Labor 3000000 Job construction ov...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started