Tora Co plans to produce 1500 units in July. Each unit requires three hours of direct labot. The direct labor rate is 13 per hour
Tora Co plans to produce 1500 units in July. Each unit requires three hours of direct labot. The direct labor rate is 13 per hour Prepare e direct labor budget for July TORA CO. Direct Labor Budget For Month Ended July 31 Budget production (units) 1.100lus Totabor hours needed Budget direct labor cost