Question
Torello Corporation manufactures two products: Product H95V and Product V93N. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing
Torello Corporation manufactures two products: Product H95V and Product V93N. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products H95V and V93N.
Activity Cost Pool | Activity Measure | Total Cost | Total Activity | ||
Machining | Machine-hours | $ | 242,000 | 11,000 | MHs |
Machine setups | Number of setups | $ | 140,000 | 350 | setups |
Product design | Number of products | $ | 70,000 | 2 | products |
Order size | Direct labor-hours | $ | 270,000 | 10,000 | DLHs |
Activity Measure | Product H95V | Product V93N |
Machine-hours | 6,000 | 5,000 |
Number of setups | 250 | 100 |
Number of products | 1 | 1 |
Direct labor-hours | 6,000 | 4,000 |
Using the plantwide overhead rate, how much manufacturing overhead cost would be allocated to Product V93N?
rev: 03_17_2018_QC_CS-119201
Multiple Choice
-
$429,000
-
$433,200
-
$288,800
-
$361,000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started