Question

1 Approved Answer

total by cost category: labour =$ 772,891 hardware = $567400 software = $ 38000 testing = $76400 reserves = $144169 (10% of total estimate) total

total by cost category:
labour =$ 772,891
hardware = $567400
software = $ 38000
testing = $76400
reserves = $144169 (10% of total estimate)
total project cost estimate = $1598860
image text in transcribed
Q: prepare a quarterly cash budget
The consultant will bill BBCC quarterly using the following completion rates. The amount is considered due at the end of each quarter for the year. Note that hardware and software costs are billed in total at the beginning of the phase they are implemented. All other costs are based on percentage completion of the phase. YTD % completion Analysis Design Implementation January 25% 0 0 February 35% 10% 0 March 50% 20% April 60% 25% 0 May 75% 30% 0 June 85% 40% 10% July 85% 45% 20% August 85% 50% 25% September 90% 60% 40% October 95% 70% 50% November 100% 80% 60% December 100% 75% The cash budget should account for these costs as billed by the consultant. The consultant will bill BBCC quarterly using the following completion rates. The amount is considered due at the end of each quarter for the year. Note that hardware and software costs are billed in total at the beginning of the phase they are implemented. All other costs are based on percentage completion of the phase. YTD % completion Analysis Design Implementation January 25% 0 0 February 35% 10% 0 March 50% 20% April 60% 25% 0 May 75% 30% 0 June 85% 40% 10% July 85% 45% 20% August 85% 50% 25% September 90% 60% 40% October 95% 70% 50% November 100% 80% 60% December 100% 75% The cash budget should account for these costs as billed by the consultant

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions

Question

What is the purpose of risk management industry standards?

Answered: 1 week ago

Question

5. Understand how cultural values influence conflict behavior.

Answered: 1 week ago

Question

e. What do you know about your ethnic background?

Answered: 1 week ago