Question
Town of Eden Bay - Part 2 The town of Eden Bay owns and maintains a fleet of vehicles. You are a systems analyst reporting
Town of Eden Bay - Part 2
The town of Eden Bay owns and maintains a fleet of vehicles. You are a systems analyst reporting to Dawn, the towns IT manager.
Background
Eden Bay is a medium-sized municipality. The town has grown rapidly, and so has the demand for town services. Eden Bay currently owns 90 vehicles, which the towns equipment department maintains. The fleet includes police cars, sanitation trucks, fire trucks, and other vehicles assigned to town employees. The maintenance budget has risen sharply in recent years, and people are asking whether the town should continue to perform its own maintenance or outsource it to private firms. Note: Non-emergency services town employees do not work on weekends.
In the first part of the case, you planned a preliminary investigation for a new information system that would cut costs and improve maintenance efficiency. Based on your investigation, Dawn wants to move forward, and she asked you to help her present a budget request at the next Town Council meeting. She suggested the following to-do list:
- First, double-check the cost and benefit data we will need for the proposal (4 days).
- Then, start two tasks at the same time: send an e-mail message to the Town Council requesting that the proposal be placed on the agenda (1 day), and develop the proposal itself, including all necessary documents and charts (6 days).
- As soon as the proposal is complete, start work on two tasks at once: print copies of handout material for the meeting (2 days) and develop a PowerPoint presentation (5 days).
- When the presentation is ready, conduct a rehearsal for the Council meeting. (2 days).
- Finally, when the rehearsal is done and the handout material is ready, help Dawn deliver the presentation. (1 day).
Tasks:
- Analyze the fact situation carefully to identify any tasks that are dependent on other tasks.
- Create Gantt and PERT charts using project management software to show the project. Use Gantt Project or MS Project to develop the charts.
- Optional - You may use want to organize the tasks before entering into the project management software. If the durations and dependencies are correctly specified in your project management file, then the critical path will also be correct - and that's a good thing. To earn full credit the critical path must be correct.
Task number
Task Name
Duration
Predecessors Task Number(s)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started