Toyota evaluates standard costing with standard material cost per unit $520, actual material cost per unit $540, standard units 11,000, actual units 10,500. Requirements: Calculate
- Toyota evaluates standard costing with standard material cost per unit $520, actual material cost per unit $540, standard units 11,000, actual units 10,500.
- Requirements:
- Calculate the material price variance.
- Calculate the material quantity variance.
- Prepare a variance analysis report.
- Suggest improvements for material cost control.