Toys are manufactured in a two-stage process. The first stage has a processing time of 8 minutes per unit (when producing) and requires a 38
Toys are manufactured in a two-stage process. The first stage has a processing time of 8 minutes per unit (when producing) and requires a 38 minute setup for each batch. The second stage has a capacity of 9 toys per hour and has no setup time. What is the capacity of the process (in units per hour) if the batch size is 70 ? Note: Do not round your intermediate calculations. Round your answer to 2 decimal places