Tozer construction company contracted with the Moncton airport authorities to construct a new runway at the Moncton international airport 38000,000.Tozer's accounting year ends on December

Tozer construction company contracted with the Moncton airport authorities to construct a new runway at the Moncton international airport 38000,000.Tozer's accounting year ends on December 31.work begun under the contact on July 1,2016 and was just completed on the 9th of October 2018 .constrction activities are summarized below by year :

2016. 2017

construction costs incurred in current year 14,4000,000. $72,000,000

additional estimated costs to complete 49,600,000. 16,800,000

progress Billings 12,000,000 18,000,000

cash received 11,200,000 15,200,000

Tozer recognizes revenue on a percentage -of -completion basis , using costs for estimating the appropriate percentage completed .

determine the amount of revenue and gross profit that Tozer construction company recognized in 2016 and 2017 respectively

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting For Dummies

Authors: Mark P Holtzman, Karen Schoenebeck

1st Edition

1118116429, 978-1118116425

More Books

Students also viewed these Accounting questions

Question

1. Too understand personal motivation.

Answered: 1 week ago