Question

1 Approved Answer

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is

image text in transcribedimage text in transcribed
image text in transcribed
image text in transcribed
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. The estimated time along the critical path is 90 days with a project variance of 20 . What due date will give the project a 0.85 probability of completion? Select the range that includes the corresponding completion time in days. Standard Normal Table between 100.5 days and 105.5 days between 95.5 days and 100.5 days more than 105.5 days between 90 days and 95.5 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introductory Financial Accounting For Business

Authors: Thomas Edmonds, Christopher Edmonds, Mark Edmonds, Jennifer Edmonds, Philip Olds

2nd Edition

1260575306, 978-1260575309

More Books

Students also viewed these Accounting questions

Question

2. What types of information are we collecting?

Answered: 1 week ago

Question

5. How quickly can we manage to collect the information?

Answered: 1 week ago

Question

3. Tactical/strategic information.

Answered: 1 week ago