Question 7 (6 marks) Precision Construction Co has agreed to build a 10 storey office building for MB Limited. The contract is for $15 million

image text in transcribed
Question 7 (6 marks) Precision Construction Co has agreed to build a 10 storey office building for MB Limited. The contract is for $15 million with progress payments being made by MB Limited as the construction proceeds. The construction begins in February 2018 and is completed in December 2020. Assume that MB Limited will own the office building over the period of construction and that Precision Construction Co. uses the percentage of completion method for construction contracts. Data on costs incurred estimated costs to complete, progress billings, and progress payments over the period of construction are as follows. (amounts are in $000's) 2018 2019 2020 Costs incurred this period $1,560 $7,815 $3,885 Costs incurred to date 1,560 9,375 13,260 Estimated costs to complete the project 10,440 3.125 Progress billings this period 1,200 6,000 7,800 Progress payments received this period 7 125 7,875 Required: Calculate the revenue to be recognized and gross profit (in dollars) for 2018 and 2019. Where applicable round your percentages to the nearest whole percent. 0 0 2018 2019

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Reform In Transition And Developing Economies

Authors: Robert W. McGee

1st Edition

0387257071, 9780387257075

More Books

Students also viewed these Accounting questions

Question

Solve each inequality, and graph the solution set. 4x90

Answered: 1 week ago

Question

An action plan is prepared.

Answered: 1 week ago