SECTION 12.2-PROJECT REVIEW Read the project review below and answer the questions that follow. A construction project for an assisted living center was reviewed after it was completed. A number of areas caused a variety of problems to occur on the project. During the review, it was determined that the following areas needed attention: - Extreme winter weather was encountened when the building envelope was being enclosed, delaying the project by 30 days. In hindsight, it was determined that if the project schedule had been adjusted to allow for concurrent activities with the building systems rough-in, the trailding eavelope eould have been started 30 diys earlice, and thic bad weather delay could have beea avoided. - The baseline schedule appeared to have a number of open-ended activities, including one that was sigaificant, requiring many adjustments to keep the project on schedule. - Unnecessary stacking of the trades created safety issues when overbead work conflicted with wock that was taking place below it. - The excavation subcontractor did not perform well and required an excessive amount of time and effort by the management team to ensure the subcontractor met the safety and quality levels required for the project. - During the review, it was unclear whether the client was satisfied with the rewult of the assisted living center. 1. What lessons can be learned from the assistod living center project regarding extreme weather events? 2. How can the situation with open-ended activities be avoided in future? 3. What should be done to ensure the stacking of trades problem does not recur? 4. How can subcontractor issues like those that occurred on this project provide helpful information for future projects? 5. What steps should be taken to ensure the construction company fully understands the satisfaction level of its clients