Question
Treco Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Materials: Standard:
Treco Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below:
Materials:
Standard: 2m @ $2.25 per m = $4.50
Actual: 2.1 m @ $2.40 per m= $5.04
Direct labor:
Standard: 1.5 hrs. @ $9.00 per hr = $13.50
Actual: 1.4 hrs. @ $9.75 per hr= $13.65
Variable overhead:
Standard: 1.5 hrs. @ $5.10 per hr. ...= $7.65
Actual: 1.4 hrs. @ $4.6S per hr. ...= $6.51
Calculate the following:
A)Material price variance
B)Material quantity variance
C)Direct labour rate variance
D)Direct labour efficiency variance
E) Variable Overhead spending Variance
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started