Question

1 Approved Answer

Treco Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below: Materials: Standard:

Treco Company's standard and actual costs per unit for the most recent period, during which 400 units were actually produced, are given below:

Materials:

Standard: 2m @ $2.25 per m = $4.50

Actual: 2.1 m @ $2.40 per m= $5.04

Direct labor:

Standard: 1.5 hrs. @ $9.00 per hr = $13.50

Actual: 1.4 hrs. @ $9.75 per hr= $13.65

Variable overhead:

Standard: 1.5 hrs. @ $5.10 per hr. ...= $7.65

Actual: 1.4 hrs. @ $4.6S per hr. ...= $6.51

Calculate the following:

A)Material price variance

B)Material quantity variance

C)Direct labour rate variance

D)Direct labour efficiency variance

E) Variable Overhead spending Variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bookkeeping All In One For Dummies

Authors: Consumer Dummies

1st Edition

1119094216, 978-1119094210

More Books

Students also viewed these Accounting questions

Question

How do you develop a common ground with your audience?

Answered: 1 week ago

Question

1. What do I want to achieve?

Answered: 1 week ago

Question

3. What is my goal?

Answered: 1 week ago