Question

1 Approved Answer

Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.00 per Ib.) $ 150.00 Direct labor (7

Trico Company set the following standard unit costs for its single product.

Direct materials (30 Ibs. @ $5.00 per Ib.) $ 150.00
Direct labor (7 hrs. @ $14 per hr.) 98.00
Factory overheadvariable (7 hrs. @ $7 per hr.) 49.00
Factory overheadfixed (7 hrs. @ $9 per hr.) 63.00
Total standard cost $ 360.00

The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 61,000 units per quarter. The following flexible budget information is available.

Operating Levels
70% 80% 90%
Production in units 42,700 48,800 54,900
Standard direct labor hours 298,900 341,600 384,300
Budgeted overhead
Fixed factory overhead $ 3,074,400 $ 3,074,400 $ 3,074,400
Variable factory overhead $ 2,092,300 $ 2,391,200 $ 2,690,100

During the current quarter, the company operated at 90% of capacity and produced 54,900 units of product; actual direct labor totaled 316,300 hours. Units produced were assigned the following standard costs.

Direct materials (1,647,000 Ibs. @ $5.00 per Ib.) $ 8,235,000
Direct labor (384,300 hrs. @ $14 per hr.) 5,380,200
Factory overhead (384,300 hrs. @ $16 per hr.) 6,148,800
Total standard cost $ 19,764,000

Actual costs incurred during the current quarter follow.

Direct materials (1,364,000 Ibs. @ $7.80 per lb.) $ 10,639,200
Direct labor (316,300 hrs. @ $11.10 per hr.) 3,510,930
Fixed factory overhead costs 2,348,400
Variable factory overhead costs 2,742,200
Total actual costs $ 19,240,730
image text in transcribedimage text in transcribedimage text in transcribed
(a) Compute the variable overhead spending and efficiency variances. (Round "cost per unit" and "rate per hour" answers to 2 decimal places.) Actual Variable OH Cost Flexible Budget Standard Cost (VOH applied) b) Compute the fixed overhead spending and volume variances. (Round "cost per unit" and "rate per hour" answers to 2 decimal places.) Actual Fixed OH Cost Budgeted Overhead Standard Cost (FOH applied) (c) Compute the total overhead controllable variance. Overhead Controllable Variance Total overhead controllable variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting The Impact On Decision Makers

Authors: Gary A. Porter, Curtis L. Norton

6th Edition

0324655231, 978-0324655230

More Books

Students also viewed these Accounting questions

Question

How do we forecast the firm's future cash requirements?

Answered: 1 week ago