Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Trico Company set the following standard unit costs for its single product. Direct materials (29 Ibs. @ $3.50 per Ib.) $ 101.50 Direct labor (5

Trico Company set the following standard unit costs for its single product.

Direct materials (29 Ibs. @ $3.50 per Ib.) $ 101.50
Direct labor (5 hrs. @ $8.90 per hr.) 44.50
Factory overheadvariable (5 hrs. @ $5.30 per hr.) 26.50
Factory overheadfixed (5 hrs. @ $7.30 per hr.) 36.50
Total standard cost $ 209.00

The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 68,000 units per quarter. The following flexible budget information is available.

Operating Levels
70% 80% 90%
Production in units 47,600 54,400 61,200
Standard direct labor hours 238,000 272,000 306,000
Budgeted overhead
Fixed factory overhead $ 1,985,600 $ 1,985,600 $ 1,985,600
Variable factory overhead $ 1,261,400 $ 1,441,600 $ 1,621,800

During the current quarter, the company operated at 70% of capacity and produced 47,600 units of product; actual direct labor totaled 236,600 hours. Units produced were assigned the following standard costs:

Direct materials (1,380,400 Ibs. @ $3.50 per Ib.) $ 4,831,400
Direct labor (238,000 hrs. @ $8.90 per hr.) 2,118,200
Factory overhead (238,000 hrs. @ $12.60 per hr.) 2,998,800
Total standard cost $ 9,948,400

Actual costs incurred during the current quarter follow:

Direct materials (1,327,400 Ibs. @ $3.75 per lb.) $ 4,977,750
Direct labor (236,600 hrs. @ $8.67 per hr.) 2,051,322
Fixed factory overhead costs 1,928,600
Variable factory overhead costs 1,218,490
Total actual costs $ 10,176,162
Actual Variable OH Cost Flexible Budget Standard Cost (VOH applied)
AH x AVR AH x SVR SH x SVR
x x x
Variable overhead spending variance
Variable overhead efficiency variance
Actual Fixed OH Cost Budgeted Overhead Standard Cost (FOH applied)
AH x AFR SH x SFR
x x
Fixed overhead spending variance Favorable
Fixed overhead volume variance Unfavorable
Total fixed overhead cost variance Unfavorable
Overhead Controllable Variance
Total overhead variance
Fixed overhead volume variance
Overhead controllable variance
Total overhead controllable variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions