Tri-State Mill uses a special sander to finish lumber. Data on the sander and its usage follow: Cost Driver Rate Cost Driver Volume Resources used
Tri-State Mill uses a special sander to finish lumber. Data on the sander and its usage follow:
Cost Driver Rate Cost Driver Volume
Resources used
Energy $ 0.90 per machine-hour 6,000 machine-hours
Repairs $ 16.00 per job 600 jobs
Resources supplied
Energy $ 6,900 Repairs 12,000
Required: Compute unused resource capacity in energy and repairs for Tri-State Mill.