Question
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of
90.
The projected demand, lot size, and time standards are shown in the following table:
The shop currently works 8 hours a day, 5 days a week,
48
weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the firm's current capacity cushion?Part 2The number of workstations required next year is
enter your response here.
(Enter
your response rounded up to the next whole
number.)
Item | Touring | Mountain |
Demand forecast | 4,000 units/year | 10,000 units/year |
Lot size | 80 units | 90 units |
Standard processing time | 0.20 hour/unit | 0.25 hour/unit |
Standard setup time | 2 hours/lot | 3 hours/lot |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started