Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one
Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity should be crashed first, adding to project cost. Activity One Two OA. Two, $500 OB. One; $6,800 OC. Two; $5,000 D. One; $800 E. One or Two should be crashed; $1,300 Normal Time 8 days 10 days Normal Cost $6,000 $4,000 Crash Time 7 days 8 days Crash Cost $6,800 $5,000