Question: Two mutually exclusive projects have the following positive NPVs and project lives: please show work project A: npv=5000; life=3 years project B: npv=6500; life=5 years
Two mutually exclusive projects have the following positive NPVs and project lives: please show work
project A: npv=5000; life=3 years
project B: npv=6500; life=5 years
If the cost of capital were 15%, which project would you accept?
| Project A because it has higher EAC | |
| Project B because it has higher EAC | |
| Project A because its NPV can be earned more quickly | |
| Project B because it has higher NPV |