Two of the activity cost pools for Martinez Company are (a) machining ($365,110) and (b) inspections ($51,000). Possible cost drivers are direct labor hours
Two of the activity cost pools for Martinez Company are (a) machining ($365,110) and (b) inspections ($51,000). Possible cost drivers are direct labor hours (2,640), machine hours (12,590), square footage (2,900), and number of inspections (200). Compute the overhead rate for each activity using the most relevant cost driver. Overhead Rate Machining $ Inspections per machine hour per inspection