Two project managers are discussing CPM. One of them states that determining the float of a network diagram for non-critical path activities, is a tool
Two project managers are discussing CPM. One of them states that determining the float of a network diagram for non-critical path activities, is a tool for network optimization. The other project manager states that float is the same thing as slack and the formula for calculating it is