Question
1 Approved Answer
Two systems are interconnected by two 16 MW tie lines. System A has four 30 MW generating units with forced outage rates of 10%. System
Two systems are interconnected by two 16 MW tie lines. System A has four 30 MW generating units with forced outage rates of 10%. System B has eight 15 MW generating units with forced outage rates of 8%. Calculate the expected loss of load in each system in days and in MW for a one-day period, given that the peak load in both System A and System B is 100MW,
(a) if the tie lines are 100%reliable,
(b) if the tie lines have failure rates of 5 failures/year and average repair times of 24 hours.
Step by Step Solution
★★★★★
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started