Typical project charter elements paired with the questions they answer are listed below. Which of these is NOT correct? a . Background - Answers the
Typical project charter elements paired with the questions they answer are listed below. Which of these is NOT correct? a Background Answers the question "Who?" b Resources Answers the question "How Much?" c Scope overview Answers the question "What?" d Milestone schedule Answers the question "When?"