uality improvement (QI) projects have four phases. Put them in the correct order. - Pilot: testing a change through Plan-Do-Study-Act (PDSA) cycles. - Innovation: coming
uality improvement (QI) projects have four phases. Put them in the correct order. - Pilot: testing a change through Plan-Do-Study-Act (PDSA) cycles. - Innovation: coming up with new ideas for changes. This is the phase in which teams brainstorm good ideas for changes to test. - Spread: implementing the change in several settings. - Implementation: making the change the new standard process in one defined setting