You have been informed of a new regulatory requirement that needs to be implemented when the system is delivered on the golive date. With such a tight deadline, there is a possibility that this might not be completed on time. What should you do next?
A Update the risk register.
B Perform a full impact analysis on the new regulatory requirement and submit a change request.
C Update the issue log
D Ask the product owner to reprioritize
requirements.