Una empresa compr un terreno para sus recursos naturales a un costo de $2,012,000. Se espera extraer 2.180.000 toneladas de mineral de este terreno. Se
Una empresa compr un terreno para sus recursos naturales a un costo de $2,012,000. Se espera extraer 2.180.000 toneladas de mineral de este terreno. Se espera que el valor de salvamento del terreno sea de $268,000. El gasto por agotamiento por tonelada de mineral es: $8.134. $0.923. $1.046. $7.507. $0.800.