Under a builders risk policy endorsed with delayed completion coverage-coverage for expenses to reduce loss, the insured will have coverage for expenses necessarily incurred to

Under a builders risk policy endorsed with delayed completion coverage-coverage for expenses to reduce loss, the insured will have coverage for expenses necessarily incurred to minimize or avoid a delay in completion only if 


a. the loss was unavoidable. 


b. the expenditures actually reduce the amount otherwise payable for the delay. 


c. the loss was not the fault of the insured. 


d. the loss was unforeseeable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

The correct answer is b the expenditures actually re... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Smith and Roberson Business Law

Authors: Richard A. Mann, Barry S. Roberts

15th Edition

1285141903, 1285141903, 9781285141909, 978-0538473637

More Books

Students also viewed these Accounting questions