units Produced 131,200 standard direct labor hours per unit 0.2 standard variable overhead rate (per direct labor hour) 3.4 actual variable overhead costs $88,670.00 actual
units Produced | 131,200 |
standard direct labor hours per unit | 0.2 |
standard variable overhead rate (per direct labor hour) | 3.4 |
actual variable overhead costs | $88,670.00 |
actual hours worked | 26,350 |
1. Calculate the variable overhead spending variance using the formula approach. (If you compute the actual variable overhead rate, carry your computations out to five significant digits and round the variance to the nearest dollar.)
2. Calculate the variable overhead efficiency variance using the formula approach.
3. Calculate the variable overhead spending variance and variable overhead efficiency variance using the three-pronged graphical approach.
- Variable Overhead Spending Variance = ? | ||
-Variable Overhead Efficiency Variance = ?
***** i especially need help with 2 and the Variable Overhead Efficiency Variance in #3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started