Urenr!!! Please answer with detialed calculation process ASAP, thank you! The following standards have been established for a raw material used to make product O84:

Urenr!!! Please answer with detialed calculation process ASAP, thank you!

The following standards have been established for a raw material used to make product O84:

Standard quantity of the material per unit of output 8.4 meters
Standard price of the material $ 19.50 per meter

The following data pertain to a recent month's operations:

Actual material purchased 4,700 meters
Actual cost of material purchased $ 95,880
Actual material used in production 4,400 meters
Actual output 630 units of product O84

The direct materials purchases variance is computed when the materials are purchased.

Required:

a. What is the materials price variance for the month?

b. What is the materials quantity variance for the month?

(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)

image text in transcribed

The following standards have been established for a raw material used to make product 084: Standard quantity of the material per unit of output Standard price of the material 8.4 meters $ 19.50 per meter The following data pertain to a recent month's operations: Actual material purchased Actual cost of material purchased Actual material used in production Actual output 4,700 meters $ 95,880 4,400 meters 630 units of product 084 The direct materials purchases variance is computed when the materials are purchased. Required: a. What is the materials price variance for the month? b. What is the materials quantity variance for the month? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.) a. Materials price variance b. Materials quantity variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

IT And European Bank Performance

Authors: E. Beccalli

1st Edition

0230006949, 9780230006942

More Books

Students also viewed these Accounting questions

Question

Draw a labelled diagram of the Dicot stem.

Answered: 1 week ago

Question

Is your management system defined?

Answered: 1 week ago

Question

Do you have a comprehensive communication plan for your strategy?

Answered: 1 week ago

Question

Do you have sufficiently ambitious milestones?

Answered: 1 week ago