Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Use learning curve theory and prepare a cost bid for 15 Starlight rocket launchers given the following data for the prototype (i.e., the model). You

  1. Use learning curve theory and prepare a cost bid for 15 Starlight rocket launchers given the following data for the prototype (i.e., the model). You must prepare a separate bid using (a) the cumulative average-time learning model, and (b) the individual unit-time learning model.

The prototype took 2,000 hours to produce and has the following cost information. The prototype can be sold as a part of the contract.

Direct materials $600,000

Direct labor (2,000 hours @ $200 per hour) $400,000 Variable direct manufacturing overhead (2,000 hours @ $100) $200,000 Other manufacturing overhead (20% of direct cost) $240,000

$1,440,000

(i.e., 20% of direct materials, direct labor, and variable overhead)

Total Cost

In preparing each bid, integrate the learning curve into the bid by relying on the following historical data for the production of 16 Sky rocket launchers, which was the previous generation of the Starlight launchers.

Unit Number

Labor Hours

1

3900

2

3650

3

3100

4

2750

5

2450

6

2475

7

2200

8

2100

9

2150

10

2100

11

1900

12

1850

13

1775

14

1800

15

1750

16

1700

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Finance questions