Question
Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table. Construct a
Use the 3-point (PERT) method to calculate the normal duration for each task (round to the nearest whole number) and enter in table.
- Construct a labeled network diagram (include duration, early/late times) on paper then insert the image below the table.
- Calculate and enter the free slack and total slack for each task in the table.
- List all paths with durations and identify the critical path.
Task | Predecessor | a | m | b | Normal duration | Free Slack | Total Slack |
A | --- | 3 | 4 | 7 | |||
B | --- | 4 | 6 | 10 | |||
C | A, B | 5 | 8 | 11 | |||
D | A | 8 | 9 | 12 | |||
E | C | 7 | 8 | 9 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Introduction to Management Science
Authors: Bernard W. Taylor
11th Edition
132751917, 978-0132751919
Students also viewed these Computer Network questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App