Use the accompanying template to help complete the following exercises and provide a comprehensive narrative to support your findings: In month 9 the following Project

Use the accompanying template to help complete the following exercises and provide a comprehensive narrative to support your findings:

  1. In month 9 the followingProject Stallioninformation is available: Actual cost is $2,000, earned value is $2,100, and planned cost is $2,400.Compute the SV and CV for the project. What is your assessment of the project on month 9?
  2. On day 51Project Bluehas an earned value of $600, an actual cost of $650, and a planned cost of $560.Compute the SV and CV for the project. What is your assessment of the project on day 51?
image text in transcribed
Task % Complete EV AC PV CV SV Cost Variance CV = EV - AC Schedule Variance SV = EV - PV 1. (PV) Planned cost of the work scheduled 2. (EV) Budgeted cost of the work completed 3. (AC) Actual cost of the work completed Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction To Management Science Quantitative Approaches To Decision Making

Authors: David R. Anderson, Dennis J. Sweeney, Thomas A. Williams, Jeffrey D. Camm, James J. Cochran

16th Edition

0357715462, 978-0357715468

More Books

Students also viewed these General Management questions

Question

=+What kind of question would you ask to encourage their response?

Answered: 1 week ago

Question

=+Does it keep the visitor reading?

Answered: 1 week ago