Use the attached Activity-on-Arrow or Activity-on-Node project networks to do the following: Calculate the ES, EF, LS, LF times for each activity. Identify the critical

Use the attached Activity-on-Arrow or Activity-on-Node project networks to do the following:

Calculate the ES, EF, LS, LF times for each activity.

Identify the critical path for the project.

Calculate the Total Slack (shared slack) in the project as well as any Free Slack for individual activities.

Revisit the network again and consider that specific resources (Resources A, B, C & D) are used for each activity and must be scheduled such that only one resource can be allocated to work on an activity at a time. The resources are identified by color and letter. For example, blue cannot be scheduled to work on two activities simultaneously. How long would it take to complete the project with these resource constraints?

Did the changes caused by resource limitations from part 4 above change the critical path? If so, explain.image text in transcribedimage text in transcribed

Simple Project Precedence Diagram Simple Project Precedence Diagram

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fuzzy Information And Engineering And Operations Research And Management

Authors: Bing-Yuan Cao

1st Edition

3642386660, 9783642386664

More Books

Students also viewed these General Management questions

Question

2. How is a command economy different from a market economy?

Answered: 1 week ago