use the correct times given please 5. TriCity Styrofoam Manufacturing TriCity Manufacturing (TCM) makes Styrofoam cups, plates and sandwich and meal containers. Next week's schedule
use the correct times given please
5. TriCity Styrofoam Manufacturing TriCity Manufacturing (TCM) makes Styrofoam cups, plates and sandwich and meal containers. Next week's schedule calls for production of 80,000 small sandwich containers, 80,000 large sandwich containers and 65,000 meal containers. To make these containers, Styrofoam sheets are melted and formed into final products using three machines MI, M2, and M3. Machine MI can process Styrofoam sheets with a maximum width of 12 inches. The width capacity of machine M2 is 16 inches and the width capacity of machine M3 is 20 inches. The small sandwich containers require 10-inch Styrofoam sheets. Thus, these containers can be produced on each of these three machines. The large sandwich containers require 12-inch Styrofoam sheets. Thus, these containers can also be produced on each of these three machines. However, the meal containers require 16-inch Styrofoam sheets. Thus, meal containers cannot be produced on MI. The waste produced depends on the machine used as reported in Table 1. I incurred in the production of all 3 containers because Styrofoam is lost in the heating and forming process as well as final trimming of the product. The amount of waste generated varies depending upon the container and the machine used. The table shows the waste in square inches for each machine product combination Machine Small sandwich Larpe Sandwich Micat NA 28 Table: Waste for each machine and product combination Production rates also depend upon the container produced and the machine used. The following Table 2 shows the production rates in units per minute for each combination of machine and product. For example, 20 small sandwich containers can be produced per minute on MI. The rate for M2 is 24 per minute and for M3 32 small sandwich containers per minute. Total time available on cach machine 35 hours MI, 35 hours M2, and 40 hours M3 Machine Small sandwich Sandwich Meal MI 29 M2 min 41 minute in M357 3mmute mit Table: Rate per minute production for each machine and product combination MI M 15 34 Costs associated with reprocessing waste are going up. TriCity wishes to minimize waste a. Determine the optimal production plan. This requires determining how many of each type of container should be manufactured on each machine. b. In your formulation there are 8 decision variables. Why are there not 9 decision variables? e. Which machines are not working to capacity? How much available time is there for each machine not at capacity d. Of all the product and machine combinations, which one in the optimal solution is sensitive to small changes in the amount of waste? c. How much would the waste have to decrease for an unused product machine Pin the optimal Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started