Question

1 Approved Answer

Use the figure and table below to answer the next three qui D (Ctrl) 8 Activity Optimistic Most Likely Pessimistic Expected Variance A 1 3.50

image text in transcribed
image text in transcribed
image text in transcribed
Use the figure and table below to answer the next three qui D (Ctrl) 8 Activity Optimistic Most Likely Pessimistic Expected Variance A 1 3.50 1.36 B 5 3.83 0.25 222 ??? D 5.33 1.00 6 3 9 What is the expected duration of activity C (select closest value)? O 4 O 6 O 8 O 2 What is the variance of activity C (select closest value - round up or down as needed)? OO 0 1 02 O 4 What is the critical path of this project? ABD O ACD O Both ABD and ACD There is no critical path

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

AQA AS Accounting Unit 2 Financial And Management Accounting

Authors: Brendan Casey

1st Edition

1500684260?, 978-1500684266

More Books

Students also viewed these Finance questions

Question

How can public relations be used successfully in IMC?

Answered: 1 week ago